WIDENING THE BRIDGES ON MAIN ROAD 89 BETWEEN MOTORWAY 5 AND VARTIUS, PHASE II
Widening the bridges on main road 89 between motorway 5 and Vartius, phase II
Grunnupplýsingar
-
Stutt lýsing á ráðgjafarfyrirtækinuWidening the road bridges on main road 89 from Paltamo to Vartius was started in the ’Widening the bridges on main road 89 between motorway 5 and Vartius’ project. Once the plans were completed in more detail, the project’s actual funding need proved to be greater than the obtained funding; therefore, a project application was submitted and funding consequently received for the project. 50 percent of the project funding was received from the European Regional Development fund and 50 percent from the Finnish Road Administration.
- Fyrirhuguð upphaf verkefnis 18.04.2005 Áætluð verklok 31.10.2006
- Lengd 18 (Mánuðum))
Fjárhagsáætlun
- Heildarfjárhagsáætlun áætlunarinnar / símtalið 1000000 Verkefni ESB-fjármögnun 1000000 Hlutfall: 100